The first section of the form is largely prefilled. Your job is to check it and fill in what is missing.

Good to know

  • The fields under inspection company, inspector and parts of Customer are taken from the assignment agreement and your profile.
  • You can overwrite them, but a correction here does not feed back to the agreement.
  • ELECTRICAL ENTERPRISE ID is normally the only field you have to fill in yourself.
  • The certificate numbers for residential, commercial and agricultural work are taken from your profile.
Screenshot of the Contractor and inspector section of the inspection form
Contractor and inspector. Electrical enterprise ID and independence level must be filled in.
Screenshot of the customer and inspection object fields
Customer and inspection object. Country is prefilled with Norway.

INDEPENDENCE LEVEL

The field is set to Choose... and must be set.

LevelMeaning
Level AIndependent
Level BLimited
Level CNot independent
Level DOwner/user

Inspection details

  • APPLICABLE REGULATION, according to when the installation was built: Rødboka / FEA (1963 til 1988) · FEB 88 · FEB 91 · FEB 92 · FEL (gjeldende fra 1999). These are Norwegian regulation names and are shown in Norwegian in the product.
  • PERFORMED PER STANDARD(S), according to which NEK 400 edition you are inspecting against: NEK 400:1998 · 2002 · 2006 · 2010 · 2014 · 2018 · 2022 · 2026
  • INSPECTION DATE * is the only field in the entire form marked with an asterisk. NEXT INSPECTION and SPECIAL CONDITIONS / NOTES are filled in as well.
Screenshot of inspection details with applicable regulation and NEK 400 edition
Inspection details. Inspection date is the only field in the form marked with an asterisk.

Tips

  • Read through the prefilled fields even if they look correct. If the agreement was written for a different address, the error follows it here.
  • Set APPLICABLE REGULATION according to when the installation was actually built, not according to today's rules. If parts of the installation were changed later, say so under SPECIAL CONDITIONS / NOTES.
  • Fill in NEXT INSPECTION straight away, while you have the installation fresh in mind. A recommended date for the next inspection belongs in the report.

I corrected a field here. Does the assignment agreement change?

No. The form and the agreement are two different documents. A correction in the form applies to the report, not to the agreement. If it is the agreement that is wrong, it has to be handled separately.